VALUE: $406,000.00
DURATION: March 2023 – October 2023
SCOPE OF WORKS:
NRG were engaged by Manuplex to install Various light and power requirements around the new ASMTI Precinct B Camp.
NRG Delivered:
- 20m Area Lighting poles
- Underground reticulation including conduit and pits
- Civil footing design
- Power Bollards
- Area Lighting Design and Installation
- Mains power and Temporary Generator Supply
- Compliance and Commissioning Documentation
OHS & QA FACTS
Environmental Incidents: 0
Safety Incidents: 0
Inspection Tests: 57