The project facilitated the transfer of raw water between the northern pits improving reliability of supply through sharing water resources. NRG completed the electrical installation for water reticulation, distribution and integration across four mine sites. Services provided included excavation works and installation of MCC and HV cables to floating pontoon syphon pumps and associated instrumentation and control, including telemetry. System incorporated SMS messaging of commands control status fault and reporting.
Equipment: excavator, bobcat, materials and consumables.
Labour: Project Manager, 2 electricians and 1 trade assistant.