FOXLEIGH MINE AUTO CARWASH

Client: Foxleigh Mine

FOXLEIGH MINE AUTO CARWASH

Client: Foxleigh Mine

VALUE: $59,000.00

DURATION: March 2023 – April 2023

NRG were successful in quoting electrical package for Foxleigh mine auto carwash, using a mixture of existing infrastructure and new control and power wiring.

NRG Delivered:

  • Underground reticulation including conduit and cabling
  • Integration with existing infrastructure
  • Design of cable tray support system
  • Design of control wiring system to achieve customer requirements
  • Testing and configuration of wash cycles and PLC control
  • Backup system for a case of site communication drop out the carwash is still useable
  • Commissioning of float switches, swipe card access system and remote start of generator

OHS & QA FACTS

Environmental Incidents: 0
Safety Incidents: 0
Inspection Tests: 31