VALUE: $1,225,000.00
DURATION: March 2024 – August 2024
NRG were engaged by Blackwater Mine, operated by Whitehaven Coal, to complete the Electrical package for the Major Shutdown on Dragline 38.
NRG Provided 1 x Electrical Coordinator, 3 x Electrical Supervisors and 19 x Electricians.
Major Electrical Scope Items:
- DC Drive System Upgrade
- Upgrade from 1x 275kVA Transformer to 3x 120kVA
- Upgrade from GE DC 2000 Drives to Siemens Sinamic SRA80
- Rewire all drive cabinets
- Rewire of Power Cables to and from all Isolation Transformers incl. New Reticulation
- Install of 2x Motor Field Trimming Panels
- Complete Boom Rewire
- Complete Cabin/Kitchen Rewire
- Twiflex Brake Upgrade
- Electrical Service of HV Switchboards
- Replacement of House Fan and Bleed Duct Motors
- Complete Vendor Equipment Require (Fire Systems, CCTV, Structural Monitoring, Payload Monitoring)
- Cab & PCR A/C Overhaul
- Complete Generator Replacement and Sync Motor Overhaul
- Complete Lube Panel & Air compressor Overhaul
- Complete Motor Replacement (Hoist, Drag, Swing, Propel) Including Blowers & Oil Pumps
- Area Lighting Design and Installation
- Management of Commissioning Documentation
- Site set-up and decommissioning of Shutdown Offices.
OHS & QA FACTS
Environmental Incidents: 0
Safety Incidents: 0
Personal Risk Assessments: 2,394
JSA’s: 76
Field Leadership Completed: 162
Inspection Tests: 857